24 Mar The construction is at the last phase

The Construction Work Is At The Last Phase. March 18th

The construction work of Shree Prajawasti Primary School, is at the last phase of the completion of the work though there were different challenges and obstacles on the way during the construction period.

.

It is expected to be completed on March 30th. Our project coordinator Swestha Dhunjel visited the field

CONSTRUCTION UPDATE Till 3rd March the work of stone masonry for foundation of classroom blocks followed by the Damp Proof Concreting (DPC) over the masonry was completed followed by the completion of started bricks work of the office & library blocks. Till date the following progress has been made in the construction works of the site.
• Completion of brick masonry works of the classroom blocks.
• Completions of stone masonry works as well as the bricks work on the foundation at the extended room of the office & library blocks.
• Installation of trusses and steel posts in the extended room in office block.
• Installation of remaining GI sheets on the classroom & additional blocks are in progress and is expected to be complete by 30th March, 2016.

Office & library blocks along with the extended additional block after completion of stone masonry works &DPC on the foundation.